2022-2027 Bond Project: West College Link (St. Mary’s to Memorial High School to Zarzamora Creek)
2022-2027 Bond Project: West College Link (St. Mary’s to Memorial High School to Zarzamora Creek)
This Project includes a proposed shared use path 12' wide along the east side of Memorial Street (Culebra to Mayberry) to connect to existing trails at Zarzamora Creek, and to St. Mary’s University.
Project Type: Streets, Sidewalks & Parks
Phase: Design Phase
Project Budget: $4.7 Million
Project Contact: Tania Mendoza - (210) 207-6905
Estimated Construction Timeline: Spring 2025-Summer 2026
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
Associated Projects:
Project Limits:
West College Link (St. Mary’s to Memorial High School to Zarzamora Creek)
You are invited to the following Pre-Construction Public Meeting:
West College Link (St. Mary’s to Memorial High School to Zarzamora Creek)
Monday, February 24, 2025
6:00 p.m. – 7:00 p.m.
Memorial Branch Library
3222 Culebra Road
San Antonio, TX 78228
Join Public Works and District 5 to review the construction plans for West College Link (St. Mary’s to Memorial High School to Zarzamora Creek) Project.
For more information, please contact:
Tania Mendoza, Capital Projects Officer
210.207.6905
What you need to know
- Contractor will be closing Memorial St. from Pickford Ave. to Paramount Ave. as early as Monday, November 24, 2025 thru mid December 2025 for reconstruction work. To facilitate traffic detour routes provided on Pickford, NW 34th and Paramount Ave. West side sidewalk will be closed.
- Contractor will be closing the east side intersections at both Blueridge St. & Memorial St. and Rivas St. & Memorial St. to thru traffic for road reconstruction. To facilitate traffic detour routes provided to N. San Joaquin Ave. Sidewalk access to pedestrians will be provided.
- Sidewalk detour routes and signage provided.
- All work is subject to change and weather permitted.
- See map provided.
Roadway detour map
Overall Project Information
- This Project includes a proposed shared use path 12' wide along the east side of Memorial Street (Culebra to Mayberry) to connect to existing trails at Zarzamora Creek, and to St. Mary’s University.
- Current work includes roadway improvements, curbs and sidewalks, tree installation, irrigation and pedestrian lighting.
Memorial Street sidewalk work - East side
Memorial Street sidewalk work - South view
Memorial Street sidewalk work - South view
Memorial Street sidewalk work - North view
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.